f4ef2b2a2a docs(physics): record cutover slice C3c completion + closeout
C3c COMPLETE at 529e0e9d in the placement-cutover plan (five fix slices,
R1 dual-review round, final gates). New closeout research note. ISSUES
#276 (settle-CellId discard), #277 (route-1 far-Create radius bound),
#278 (user-session triage bundle). Register AD-60/AD-61 numeric order.

The next slice before C5 is the 6b28ff99 O(changed) collision clone
(soak convergence); C4 resumes after.

Co-Authored-By: Claude Fable 5 <noreply@anthropic.com>
2026-08-02 18:12:57 +02:00
Erik
78f1eb1896 docs(physics): record cutover slice C3b completion
C3b landed at 0934a121 with dual review PASS. The plan records the
remote-entry mechanism and its verified retail anchors; the float-gates
doc gains the port note pinning the NaN dispositions (friction's
sanctioned skip; elasticity and translucency routed exactly as the
binary; ACE's elasticity NaN divergence recorded). Every dormant C3
prerequisite is now complete — C3c, the host flip with the connected
gates, is the sole remaining piece of C3.

Co-Authored-By: Claude Fable 5 <noreply@anthropic.com>
2026-08-02 10:21:05 +02:00
Erik
d62b99509e docs(physics): record cutover slice C3a completion
C3a landed at 960373df with dual review PASS. The plan records the
conductor's five-stage sequence (verified step-for-step against retail's
entry order, with the mover-shapes-first correction the tested
preconditions forced), the convergence/wiring closures, and the two
carried findings C3c must honor. Next: C3b remote body construction at
Create, whose float-gate oracle is committed at 874d94bf.

Co-Authored-By: Claude Fable 5 <noreply@anthropic.com>
2026-08-02 09:43:32 +02:00
Erik
277ef5d032 docs(physics): decompose C3 after the flip halted with findings
The first C3 implementation pass landed C3-1 (fe02c4f5) and correctly
stopped on two structural gaps no planning document captured: the local
player's first-entry circularity (the residence opens its placement at
Create, submission needs a body, and only the zero-caller publication
chain can attach one — resolvable by the campaign handoff's own route-1
order, but no driveable state machine exists) and the absence of any
remote-creature body construction at Create time (retail builds physics
in ACCObjectMaint::CreateObject; ours arrive with first motion). The
plan now records the C3a (first-entry conductor, dormant) / C3b
(retail-anchored remote body construction at Create, dormant — its
contract must first resolve set_description's three FPU-elided
friction/translucency gates from the PDB-paired binary) / C3c (the
actual host flips + connected gates) decomposition.

Co-Authored-By: Claude Fable 5 <noreply@anthropic.com>
2026-08-02 08:17:23 +02:00
Erik
a32aba35d1 docs(physics): record cutover slice C2 completion
C2 landed at 63c601ff with dual review PASS after two fix rounds. The
plan records the halved allocation result and tightened gate, the
class-wide token-based staleness rework the pooling forced, the
documented residual floor (Core-side ~520 B/op deferred to the C3
activation gate as a possible C2b), and the two review maintenance
notes. Next slice: C3, the spawn-frequency host cutover of routes 1+8.

Co-Authored-By: Claude Fable 5 <noreply@anthropic.com>
2026-08-02 07:43:30 +02:00
Erik
6460596b56 docs(physics): C1 satisfied by the existing publication mechanism
The C1 body-writer research found the atomic controller/body transaction
already built and tested: RuntimeLocalPlayerPhysicsPublicationState plus
the dormant local-activation family implement the sanctioned
off-canonical-prepare + validated-atomic-commit shape end-to-end, with
zero production callers. The committed writer map records the six
canonical body writers, the two host escape hatches (the public
Controller setter both hosts write directly; App's object-clock facade
bypasses), the headless prepared-collision fragility, and both hosts'
construction divergences. C1 therefore collapses into C3's route-1 flip
— the remaining work is production wiring, not mechanism design — and
C2 (the placement allocation budget) becomes the next slice.

Co-Authored-By: Claude Fable 5 <noreply@anthropic.com>
2026-08-02 05:33:29 +02:00
Erik
ae29639307 docs(physics): record cutover slice C0 completion
C0 landed at 67f63e85 with dual review PASS; the plan now records its
delivered seam (acknowledge-only ExecutorCompleted receipts through the
one placement stream, retail-exact live-input derivation, the chained
authored-mover preparation, the cancellation-symmetry hardening) and the
three C3 prerequisites its reviews surfaced: the internal-only completion
receipt surface, the per-Execute distance-freshness deferral, and the
SendAutonomyLevelEvent obligation on any future autonomy-level host
exposure. Next slice: C1, the atomic controller/body publication.

Co-Authored-By: Claude Fable 5 <noreply@anthropic.com>
2026-08-02 05:22:51 +02:00
Erik
27e05b99e4 docs(physics): plan the placement production cutover
The continuation executor (5db3de3c) completed the dormant residence
mechanism; the cutover is the campaign leg that makes it production truth.
The committed 8-route inventory maps every duplicate placement authority in
both hosts with exact call chains, confirms the placement-receipt observer
seam is fully built but unattached, and surfaces five pre-cutover gaps the
shipped mechanism cannot yet express (executor-to-channel bridge, atomic
controller/body publication, the 1,880 B/op activation budget, Runtime-side
live-input derivation, the portal-authority adapter). The plan decomposes
the cutover into C0-C5 bisectable slices under the campaign's standing
contract/dual-review/gate discipline, ending at the connected routes and
the user visual matrix that retire AP-1/AD-1.

Co-Authored-By: Claude Fable 5 <noreply@anthropic.com>
2026-08-02 04:10:38 +02:00