Erik 211350b8a6 docs(render): Phase U.4c — implementation plan (stabilize portal visibility)
Five tasks: (1) RED apparatus reproducing the doorway flap on a synthetic
C0->C1->C2(exit) chain; (2) Layer 1 LoadedCell.VisibleCells + SeenOutside
plumbing; (3) oracle-ported PVS grounding of set membership (the fix, gated by
task 1); (4) seen_outside invariants (sealed=empty, threshold=stable); (5)
live [vis] + visual gate. Task 3 is a faithful port (add_views 433382 /
InitCell 432896 / ClipPortals 433572), pseudocode-first, not fabricated.

Co-Authored-By: Claude Opus 4.8 (1M context) <noreply@anthropic.com>
2026-05-31 09:53:38 +02:00
..
architecture ship(O): Phase O — DatPath Unification — SHIPPED 2026-05-21 17:41:15 +02:00
audit docs: update audit — Sprint 1 items verified (sequence counters + scenery LCG) 2026-04-13 13:51:39 +02:00
plans docs: abandon two-pipe render approach; scope Phase U (unified retail-faithful pipeline) 2026-05-30 11:35:41 +02:00
research docs(render): Phase U.4 shipped (indoor rendering verified) + flap handoff 2026-05-31 09:16:35 +02:00
superpowers docs(render): Phase U.4c — implementation plan (stabilize portal visibility) 2026-05-31 09:53:38 +02:00
bugs.md docs: update bugs.md — close BUG-002/003/004, add BUG-005/006/007 2026-04-14 12:17:31 +02:00
ISSUES.md fix(render): Phase U.2b — resolve reciprocal portal by other_portal_id (retail 433557) 2026-05-30 16:56:00 +02:00